Free Engineering Calculator

Fastener Total Cost of Ownership Calculator

Total cost = units x price + units x defect rate x failure cost + admin cost. With the default numbers, a $0.05 part with 2% defects costs $76,500 a year against $12,000 for a $0.07 part with 0.1% defects. Enter your own figures below.

99.9%

Accuracy Rate

24/7

Global Ops

200+

Containers/Yr

Understanding the TCO Model

At Component Solutions Group, we look beyond the piece price. In the fastener industry, the invoice price of a component typically represents only about 15% of the total cost (the 15/85 rule, as published by Bossard). The remaining 85% is hidden in logistics, quality control, assembly time, and inventory management.

Our TCO approach identifies “soft cost” leakage and converts them into hard savings through optimized supply chain solutions and engineering support.

The 15/85 Rule. 15% Visible: Purchase Price. 85% Hidden: Procurement, Receiving, Inspection, Storage, In-place assembly, and Overhead.

Compare Two Suppliers on Total Cost

Use the utility below to convert technical specifications for your TCO analysis. Accurate data entry ensures the integrity of your cost modeling.

Total Cost of Ownership

Calculate the true impact of supplier quality on your bottom line.

Supplier A Total Annual Cost

$0
Quality Risk Impact:$0

Supplier B Total Annual Cost

$0
Quality Risk Impact:$0

Potential Annual Savings

$0

*Analysis includes purchase price, quality risk impact, and administrative burden.

How to Use the Fastener TCO Calculator

  • Enter your annual consumption in units.
  • Enter each supplier’s unit price.
  • Enter each supplier’s defect rate in percent, from your incoming inspection or line data.
  • Enter what one defective part costs you when it is found (sorting, rework, downtime, scrap).
  • Enter the annual admin overhead and read each supplier’s total and the saving.

Formula and Worked Example

For each supplier: Total = Q x Price + Q x Defect rate x Failure cost + Admin. Admin is the same figure for both suppliers in this tool, so it does not change the saving.

100,000 units a yearSupplier ASupplier B
Unit price$0.050$0.070
Purchase cost$5,000$7,000
Defect rate2.0%0.1%
Quality cost at $35 per failure$70,000$3,500
Admin$1,500$1,500
Total annual cost$76,500$12,000
Cost per unit$0.765$0.120

The cheaper part costs $64,500 more a year. The failure cost drives the result, so use a real figure from your own sorting, rework or line-stop records.

TCO Cost Drivers

Cost CategoryDescriptionCSG Impact
ProcurementPO processing, sourcing, and vendor management.Consolidated vendor base.
InventoryCarrying costs, obsolescence, and floor space.VMI & JIT delivery programs.
QualityRework, sorting, and line shutdowns.Zero-defect quality assurance.
AssemblyIn-place installation time and tool wear.Value-added engineering.

Next Steps

Check procurement, inventory and quality savings, find the right fastener family, talk to our engineers, or request a quote.

Ready to Reduce Your Total Costs?

Our engineering team can perform a full site audit to identify specific TCO reduction opportunities in your assembly line.

Prefer to talk it through?